South Korea drafts 50MW grid-assessment exemption for non-capital AIDCs
The draft would require construction, operating and change notifications, while special-zone applications would face a 90-day ministry review.
South Korea’s Ministry of Science and ICT (MSIT) on 20 November published draft Enforcement Decree and Enforcement Rules for the Special Act on Promoting the Artificial Intelligence Data Center Industry. The proposals would exempt newly built, expanded or converted artificial intelligence data centres (AIDCs) in non-capital regions from a power grid impact assessment where contracted power is 50MW or less. The Act and planned subordinate legislation are due to take effect on 10 March 2027. The drafts are not final, and comments close on 30 December 2026.
For operators, eligibility for the exemption and other statutory support would depend on satisfying the proposed AIDC definition and filing requirements. The draft covers facilities with AI accelerators above a prescribed scale, the power and cooling equipment needed to operate them, and a design power ratio of no more than 1.5. It also expressly includes colocation facilities that provide space and power, communications and cooling systems for AI racks owned or managed by third parties.
Eligibility and filings
The proposed notification regime divides filings into:
- a construction notification before construction begins;
- an operating notification 30 days before operations start; and
- a change notification within 30 days after the relevant change occurs.
An operator submitting a construction notification would also have to report its chosen construction start date within one year of the notification. MSIT said this is intended to prevent nominal projects from reserving statutory benefits, including the grid-assessment exemption, without starting construction.
The draft would also set response deadlines between MSIT and other authorities for integrated permit processing. If a relevant authority fails to respond within the applicable period, the process could continue on the basis of the documents submitted. The release does not state the individual response periods.
The 50MW exemption would apply only to AIDCs newly built, expanded or converted in non-capital regions. It would not create a general exemption for large-scale projects. MSIT said it plans, in consultation with the Ministry of Climate, Energy and Environment, to pursue a separate fast track under which mega-projects and AIDCs subject to integrated permitting conduct the assessment first. It also plans a simplified assessment system under which AIDCs in designated special zones would be exempt from the non-technical assessment. Those initiatives are described as plans, not current entitlements under the draft.
Special zones and local infrastructure
Local governments would apply for AIDC special-zone designation after MSIT publishes a designation plan. MSIT would review an application within 90 days before the AI Committee considers and decides the designation.
Within a special zone, central and local governments could build or fund infrastructure beyond power and water facilities. The proposed list includes roads and bridges, heat supply and energy-storage facilities, waste-heat reuse, ultra-high-speed communications, security and disaster-response systems, and facilities improving residential conditions or benefiting local residents.
The draft would also reduce AIDC ancillary parking requirements by 20% against existing standards, with local ordinances able to provide further reductions of up to 50%. The ministry plans to issue regional coexistence guidelines in the first half of 2027, including procedures for consulting residents near AIDCs.
MSIT will hold a public hearing on the proposals on 9 December 2026 at Nuri Dream Square in Seoul. Written comments remain open until 30 December, ahead of legal review intended to bring the subordinate legislation into force with the Act on 10 March 2027.
Permanent link to this Atlas analysis
Related Atlas analysis
Continue with coverage connected by market, topic and operating context.
- South KoreaSouth Korea drafts AIDC rules with 50MW grid exemption and reporting dutiesComments close on 30 December, with the subordinate legislation intended to start alongside the Act on 10 March 2027.
- AustriaAustrian FMA gains consumer lending supervision powers from 20 NovemberThe rules cover BNPL and other deferred-payment products as Austria’s consumer loan balance reaches €22.5bn, up 6.8% year-on-year.
- United StatesNevada proposes wholesale kiosk standard revisions effective 1 October 2027The draft would set a $500 daily withdrawal cap, 35-transaction histories and detailed voucher, jackpot, cash-out and exception reports.
Continue with Atlas
Move from this development into the relevant research, comparison and workflow.